Registering Property in Bangladesh, Bogra

BUILDING A WAREHOUSE
Data as of: January 2006
City: Bogra

Registration Requirements:
Procedure 1Obtain Planning Permission
Time to complete:45 days
Cost to complete:BDT 4500
Comment:
Procedure 2*Obtain certificate of ownership from Tahsil Office
Time to complete:3 days
Cost to complete:no charge
Comment:
Procedure 3*Obtain lot plan
Time to complete:7 days
Cost to complete:no charge
Comment:
Procedure 4Obtain project clearance from Department of Environment
Time to complete:30 days
Cost to complete:no charge
Comment:
Procedure 5Obtain project clearance from Civil Defense Department (Fire Service Dept)
Time to complete:90 days
Cost to complete:no charge
Comment:
Procedure 6Payment of Chowkidari (Security) Tax
Time to complete:1 day
Cost to complete:BDT 120
Comment:
Procedure 7Receive pre-construction inspection
Time to complete:1 day
Cost to complete:no charge
Comment:
Procedure 8Receive excavation work inspection
Time to complete:1 day
Cost to complete:no charge
Comment:
Procedure 9Receive foundations work inspection
Time to complete:1 day
Cost to complete:no charge
Comment:
Procedure 10Obtain approval for water connection
Time to complete:3 days
Cost to complete:BDT 1400
Comment:
Procedure 11Obtain approval for sewerage connection
Time to complete:3 days
Cost to complete:no charge
Comment:
Procedure 12Obtain electricity connection
Time to complete:30 days
Cost to complete:BDT 18000
Comment:
Procedure 13Obtain fixed telephone line
Time to complete:15 days
Cost to complete:BDT 7400
Comment:
Procedure 14Obtain Occupancy permit
Time to complete:10 days
Cost to complete:no charge
Comment: 
Note: Procedures sometimes take place simultaneously. Instances of this are marked with an asterisk (*).