Registering Property in India, Jaipur

BUILDING A WAREHOUSE
Data as of: January 2006
City: Jaipur

Registration Requirements:
Procedure 1Obtain land use permission from Jaipur development authority
Time to complete:50 days
Cost to complete:INR 8000
Comment:
Procedure 2Apply for building permit and pay initial fee
Time to complete:5 days
Cost to complete:INR 300
Comment:The company must submit the application to Jaipur Municipal Corporation along with the following documents: a) Five copies (two cloth mounted) of building plan; b) Evidence like Record of Rights (ROR) or a civil court decree as regards title and possessio
Procedure 3Obtain approval of plans (building permit) and pay final fees
Time to complete:30 days
Cost to complete:INR 26000
Comment:Application will be scrutinized. If the application is fit to be approved, a demand will be sent to you by the local authority for payment of license fee and development charges if any. The rate will depend on the proposed uses and the floor area.
Procedure 4Notify the Municipal Corporation of Jaipur before start of foundation concreting
Time to complete:35 days
Cost to complete:no charge
Comment:
Procedure 5*Receive inspection from Municipal Corporation of Jaipur
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 6*Notify the Municipal Corporation of about the completing of finishing work
Time to complete:33 days
Cost to complete:no charge
Comment:
Procedure 7*Receive inspection from Municipal Corporation of Jaipur
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 8Obtain no objection certificate from fire department
Time to complete:30 days
Cost to complete:INR 2000
Comment:
Procedure 9*Receive inspection from fire department
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 10*Apply for the use and uplift of underground water with the Rajasthan State pollution control board
Time to complete:20 days
Cost to complete:INR 1000
Comment:
Procedure 11*Receive inspection from Rajasthan State pollution control board
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 12*Obtain no objections certificate from Public Health Department
Time to complete:15 days
Cost to complete:INR 2500
Comment:
Procedure 13*Apply for sanction of power connection with Rajasthan State Electricity Board
Time to complete:45 days
Cost to complete:INR 75,000 (INR 50,000-100,000)
Comment:
Procedure 14*Receive inspection from Rajasthan State Electricity Board
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 15*Obtain water and sewage connection from Jaipur Municipal Corporation
Time to complete:40 days
Cost to complete:INR 5500
Comment:
Procedure 16*Obtain phone connection
Time to complete:7 days
Cost to complete:INR 2000
Comment:
Procedure 17Obtain completion certificate
Time to complete:45 days
Cost to complete:INR 2500
Comment:
Procedure 18*Receive final inspection from Municipality
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 19Obtain occupancy permit
Time to complete:25 days
Cost to complete:INR 30 per square meter
Comment:
Procedure 20*Receive final inspection
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment: